The following data were obtained from an in-house MIS project:

Problem 1

The following data were obtained from an in-house MIS project:

Activity Duration Predecessors

A 3 Days —

B 6 Days —

C 3 Days B

D 2 Days A

E 3 Days C,D

F 2 Days A

G 4 Days F

H 7 Days B

I 2 Days C,D

J 4 Days H,I

K 8 Days H,I

L 5 Days E,G,J

a) What are the critical path activities? (5 points)

b) What is the project’s scheduled completion time? (5 points)

c) What is the slack or float for Activity C? Show your calculations. (1 point)

d) What is the slack or float for Activity F? Show your calculations. (1 point)

e) What is the slack or float for Activity E? Show your calculations. (1 point)

f) What is the slack or float for Activity J? Show your calculations. (1 point)